Horn Addition & Remodel
- Addition of preschool & kindergarten classrooms
- New Cafeteria & kitchen
- Building wide HVAC upgrades
- Completion 8/2024
North Central Middle School
- Updates to parking lot & fire lane
- Approximately 50,000 square foot addition to accommodate additional students/staff
- Expansion of the kitchen & cafeteria
- Completion 8/2024
Northwest Middle School
- Updates to parking lot & fire lane
- Approximately 50,000 square foot addition to accommodate additional students/staff
- Expansion of the kitchen & cafeteria
- Completion 8/2024
Southeast Middle School
- Updates to parking lot & fire lane
- Approximately 50,000 square foot addition to accommodate additional students/staff
- Expansion of the kitchen & cafeteria
- Completion 8/2024
City High Remodel – Phase 3
- Remodel a portion of old cafeteria/kitchen into CTE space
- HVAC upgrades in auditorium
- Classroom remodel in C-wing, to include new flooring
- Completion 8/2024
Center for Innovation - CFI
- Classroom Area Remodel – Completion 8/2025
- Administrative Offices Remodel – Completion 12/2024
- New Board Room – Completion 12/2024
West High Addition & Remodel – Phase 3
- New & improved secure front entrance & administrative offices
- Student Commons addition
- Remodel of the Fine Arts area to include HVAC upgrades
- Completion 8/2025
Lemme, Wickham, Weber HVAC upgrades
- Upgrade buildings to Geothermal HVAC system
- Completion 8/2025
Lucas Gym Addition
- New 5,000 square foot gym addition
- Renovation of adjacent classroom & support spaces
- Completion 8/2025